Based on the feedback on naming convention and taking into account the discussions we had internally in ENTSO-E I prepared a new version of the naming convention for profile 2 (see attached or follow the link: http://cimug.ucaiug.org/Groups/ENTSO-E_IOP/SDO_2013/Shared%20Documents/310313_NamingConventionProfile2_v2.doc ). This version is now open for comments by vendors and TSOs. The assumption is that vendors do not specify the modelling needs of their users so the consultation for vendors is an early notice on expected flexibility in the tools to cope with various data exchanges and have advantage of the CIM based exchange the purpose of power system analyses and related reporting.
The consultation on the naming convention is open until 30 April 2013. The next steps will be:
- early May 2013: Finalize and implement in the profile 2 for the IOP in 2013
- naming convention will be considered approved if profile 2 is approved
- further restrictions of the naming convention related to various data exchanges due to different business processes should be agreed within 1 month after of the profile 2 approval or at least 1month before the start of implementation tests.
The feedback should be provided to: Chavdar.ivanov@entsoe.eu
Best regards
Chavdar
Chavdar Ivanov, Ph.D.
Research and Development Senior Advisor
ENTSO-E
European Network of Transmission System Operators for Electricity
Avenue de Cortenbergh 100